29 July 2011

June quarterly 2011

QUARTERLY ACTIVITIES REPORT  
ASX Release – 29 July 2011


CORPORATE 
• Cash on hand $9.021 million at 30 June 2011

AUSTRALIAN ALUMINIUM OPERATIONS UPDATE 
• Gross Quarterly Cash Receipts of $1,133,000
• Gross Quarterly Operating Cash Surplus of $46,851 with trade receivables of $1.2 million at 30 June 
• Closed-loop salt slag operations underway
• Landfill mining to commence once current stockpile of partly-processed salt slag reduced
• First shipment of AL80 awaiting departure
• Salt crystalliser under construction
• Engagement with Federal Government regarding carbon tax benefits for MHM’s recycling operations


US ALUMINIUM OPERATIONS UPDATE 
• MHM progressing with expansion into the US, targeting commencement of operations in 2012 
• Processing throughput for the first plant expected to be 200,000 to 250,000 tonnes per annum 
• Appointment of Senior US Executive – Director of Operations, North America 
• Salt slag supply contract discussions well advanced
• Engagement with parties showing interest in supplying a second salt slag recycling facility
• Decision for location of first US salt slag plant is imminent
• Testing program of 350,000 salt slag mono-fill completed, awaiting feedback from Government 
regarding reprocessing
• Permitting and engineering consultants have commenced project planning activities
• Positive meetings with senior government officials for project support, incentives and concessions
• Preliminary discussions with parties regarding non-dilutionary financing mechanisms


SILICA PROJ ECT UPDATE 
• Drilling program over Cape Sorell completed, awaiting assays
• Continued negotiation for offtake, silicon smelter discussions positive and ongoing


TASMANIAN EXPLORATION UPDATE 
• Highly encouraging first-stage drilling at Hill 99 VHMS copper-gold project
• Assays expected by end of August 2011
• Drill core studies showing stratigraphy, alteration and age of the rocks at Hill 99 comparable with 
Hellier-Fosse-Roseberry group of mines further to the north.  







AUSTRALIAN ALUMINIUM OPERATIONS UPDATE 
Financial r esults 
MHM’s Australian aluminium subsidiary, Alreco Pty Ltd delivered Gross Quarterly Cash Receipts of $1,133,000
million with a Gross Quarterly Operating Surplus of $46,851.  Alreco also had trade receivables of $1.2 million at 
30 June 2011.


Closed-loop oper ations continuing 
Closed-loop salt slag recycling operations have commenced.  This is a significant milestone for the company, 
paving the way for the global expansion of the technology.  Alreco’s profits are expected to substantially 
increase once reprocessing of Alcoa’s 160,000 tonne salt slag landfill commences.  This will occur once the 
stockpile of partly-processed salt slag on MHM’s site is reduced.


First AL80 shipment 
Alreco’s first shipment of AL80, an aluminium oxide product, has been prepared and is awaiting departure.  The 
first shipment is 800 tonnes and will be followed by monthly shipments of a minimum of 1,500 tonnes.  Alreco’s 
contract with Impex Minerals Pty Ltd provides no upper limit to the amount of AL80 that can be sold to Impex.  
During the quarter, Alreco also received additional enquiries for offtake of a substantial monthly tonnage of 
AL80 from another party. 


"Large portion of the estimated $8.6m EBIT p.a. is from the aluminium oxide sales, the first shipment is due in July then followed by minimum 1,500 tonnes per month, so September quarter will have minimum 3,800 tonnes of AL80 shipped to Impex, and if MHM receive another offtake agreement from the other interested party the revenue should increase significantly." IMO


Alreco’s AL80 product is produced from aluminium oxide, one of the commodities recovered from salt slag 
recycling.  Finding viable applications for aluminium oxide has been a major hurdle for salt slag processing.  The 
aluminium industry unsuccessfully tried for a number of years to source a high value, high volume application 
for aluminium oxide.  AL80 is produced when aluminium oxide recovered from Alreco’s salt slag operations is 
value added using an additional proprietary process.  Alreco’s off take agreement for AL80 is an event of 
significance for the global aluminium industry and its importance should not be underestimated.
MHM believes there is opportunity for additional value-adding of the AL80, to be addressed in due course.
This is a major milestone for the company as it completes MHM’s closed-loop, landfill-free salt slag processing 
technology.  MHM is seeking additional aluminium oxide for treatment with the company’s proprietary process 
to produce AL80, to sell under the off take agreement with Impex Minerals.


Salt crystalliser construction underway 
Alreco has completed an order for a salt crystallisation system to be installed at Moolap.  The system will 
recover substantial volumes of water as compared to Alreco’s current system of solar evaporation.  The 
crystalliser technology provider has indicated that the system will be operational by the end of December 2011.


Potential Carbon Tax benefits to MHM 
Alreco has  commenced  discussions with the Federal Government regarding potential benefits for salt slag 
recycling under the proposed carbon tax.


Continuing to process material f or Sims under original contract terms 
An updated processing agreement for salt slag, non-salt slag, and aluminium dross with Sims Aluminium Pty 
Ltd has not yet been finalised.  Alreco continues to receive material from Sims under the terms of the initial 
contract. 


US ALUMINIUM OPERATIONS UPDATE 
MHM’s expansion into the United States continues to advance.  The Company is extremely confident of 
establishing salt slag recycling operations in Tennessee, and will commence construction-related activities 
following finalisation of salt slag supply contracts and land acquisition.  It is expected that this first plant will 
have a throughput of 200,000 to 250,000 tonnes per annum, representing an estimated 20-25% of the salt slag 
produced by the entire US aluminium industry.  It is understood that an additional two to four salt slag recycling 
plants could be justified in the United States.




The establishment of closed-loop salt slag recycling operations in the United States will be an immensely 
positive development for the US aluminium industry, welcomed by industry stakeholders, government and 
community alike.


MHM is targeting commencement of operations during the second-half of 2012.  The exact timeframe will 
depend on the time taken to finalise supply contracts and the specifics of the chosen plant site.  MHM’s 
permitting, engineering and construction management consultants have prepared a detailed timeline for 
construction and commissioning, the details of which will be made available once all variables have been 
resolved.


MHM has also recently engaged with aluminium companies that are showing keen interest to supply salt cake  to a second salt slag recycling facility in a region to service the north-eastern United States and parts of Canada.


Appointment of Director of Operations, North America 
MHM Metals Corporation, the company’s US operating subsidiary, has appointed a Director of Operations, North 
America.  Mr John Pugh, formerly Vice President of Business Development and Vice President of Operations for 
Smelter Service Corporation, has been appointed to the role. 


Mr Pugh is widely regarded as one of the leading operations executives in the US aluminium industry and will be 
a great asset for MHM.  Smelter Service Corporation and MHM agreed that Mr Pugh’s appointment to MHM is in 
the best interests of the ongoing cooperation between the companies.  Mr Pugh holds a degree in business 
management and has 31 years management experience in the metals industries.  This includes five years with 
a manganese alloy foundry and 26 years in secondary aluminium recycling, including 21 years with Smelter 
Service Corporation. 


Salt slag supply contract negotiations  
MHM is advancing contract negotiations, with draft terms, conditions and pricing being circulated and finalised.  
MHM is hoping that the first of the contracts may be signed by the end of August 2011, and has recently hosted 
a number of potential US salt slag suppliers for site visits in Geelong.  


Tennessee site acquisition due diligence 
MHM continues to progress due diligence for Tennessee site selection, and is well advanced in the process.  
Proximity to salt slag suppliers, zoning and permitting requirements, transportation options (road, rail) and 
government incentives are all important considerations in the selection of the site.  It is anticipated that news 
regarding site acquisition should be forthcoming in the near future.


Site acquisition has taken a little longer than initially anticipated.  In May and June, MHM conducted extensive 
due diligence, agreed a purchase price and finalized terms for a property purchase contract for an 80-acre site in 
Tennessee that showed great potential.  However, sub-surface environmental assessment by MHM indicated 
that the site contained some geotechnical issues and consequently it was decided to seek alternatives.  Whilst 
this has resulted in a longer than anticipated timeframe for site acquisition, the timing has not affected MHM’s 
overall development timetable as salt slag supply contracts are still in the final stages of completion.


Government support 
MHM is positively engaged with the Tennessee state and local governments regarding concessions and 
incentives for salt slag recycling.  MHM has general terms of a financial support package, however the final 
details will depend on site selection.  A detailed overview of the incentives and concessions available to MHM 
will be provided after this time.  


Smelter Service Corp landfill testing 
The first-stage testing program of Smelter Service Corporation’s 350,000 tonne salt slag mono-fill has 
concluded.  Whilst MHM does not believe that the entire landfill can be remediated, as with the Alcoa landfill in 
Geelong, there appears to be potential to recover material.  The SSC mono-fill has some issues with soil and clay 
contamination of some finer portions of salt slag, and separation of the soils from aluminium oxides can be 
challenging.  


MHM and SSC have approached the Tennessee Department of Environment and Conservation with a number of 
proposals for remediation, which are being considered.US investor relations roadshow 


A number of meetings and presentations with US investors were held during the quarter, which were well 
received.  Additional presentations are planned in due course, particularly following execution of US salt slag 
supply contracts and Tennessee land acquisition.  As always, management efforts are best directed to achieving 
maximum return for effort and investment, and it is believed that the next US roadshow will be most effective 
following tangible contractual developments in the United States.  


SILICA PROJECT UPDATE 

High  Purity  Silica  Drilling 
MHM’s first-phase diamond drilling at the Cape Sorell High Purity Silica Project has been completed. A total of 
six short holes intersected white quartzite over a thickness of approximately 12m based on visual appearance. 
The silica rich quartzite dips approximately 50° west, and drilling was designed to test the true thickness of the 
quartzite at the North Escarpment prospect and the potential for a more extensive silica cap over mixed 
sediments including sandstone and siltstone.  Sampling and assaying of the drill core is continuing.


Of ftake Negotiation 
MHM continues to work with a number of parties concerning offtake of lump silica and silica flour, both for 
export and for utilisation in a proposed Tasmanian silicon smelter.


TASMANIAN EXPLORATION UPDATE 

Drilling of  Hi l l 99 Co p p e r-Le a d-Zinc  Prospect 
The two-hole 369 metre diamond-drilling program at MHM’s Hill 99 copper-lead-zinc prospect has completed, 
with preliminary inspection and sampling of the core by Niton XFR analyser showing highly encouraging levels
of mineralisation. The target was for copper mineralisation with zinc and gold credits in either a structural or
VHMS setting. The results to hand are extremely positive and the core is now being prepared for assay.
Hole H99-04 intersected strong quartz veining from 158m to 183m within highly altered intermediate and mafic 
volcanic rocks with disseminated chalcopyrite (copper sulphide) though parts of this section.
Hole H99-05 intersected strongly altered mafic volcanics throughout the hole. Intense quartz-carbonate veining 
is present from 118m to the end of the hole at 173m. Patchy, disseminated lead and zinc sulphides are 
associated with some of the veins. The intensity of the alteration and veining in both drill holes indicates that 
strong, mineralised hydrothermal systems have been intersected and will require follow up drilling.
Detailed studies on drill core from this and previous drill holes have shown that the stratigraphy, alteration and 
age of the rocks at Hill 99 are comparable with mineralised horizons at the Hellier-Fosse-Roseberry group of 
mines further to the north.


MHM’s ongoing exploration is consistent with the company’s strategy to continue to progress the mineral 
projects while assessing opportunities to engage with project development partners, divest or spin-off the 
mineral assets of the company at a time that maximises returns to shareholders.



Link

Chart as at 29th of July 2011

28 July 2011

MHMO Conversion

660 options has been converted into fully paid ordinary shares at $0.20 each




Daily chart as at 28/7/2011


Share price $1.04 as at 28th July 2011 
M/C $106.34m
MHM                                                                         102,252,570
MHMO expiry 31 August 2012                                  25,520,600
Unlisted Options $0.20 expiry 31 August 2012            2,131,225
                          $0.20 expiry 28 November 2013      1,100,000
                          $0.20 expiry 14 December 2013       1,000,000
                          $0.25 expiry 9 October 2014              370,000
                          $0.28 expiry 30 November 2014       1,900,000
                          $0.28 expiry 4 January 2015                100,000
                          $0.85 expiry 6 October 2015               300,000
                          $1.80 expiry 20 June 2016                   300,000
Total                                                                            134,974,395

26 July 2011

MHMO Conversion

17,500 options has been converted into fully paid ordinary shares at $0.20 each






MHM                                                                         102,251,910
MHMO expiry 31 August 2012                                  25,521,260
Unlisted Options $0.20 expiry 31 August 2012            2,131,225
                          $0.20 expiry 28 November 2013      1,100,000
                          $0.20 expiry 14 December 2013       1,000,000
                          $0.25 expiry 9 October 2014              370,000
                          $0.28 expiry 30 November 2014       1,900,000
                          $0.28 expiry 4 January 2015                100,000
                          $0.85 expiry 6 October 2015               300,000
                          $1.80 expiry 20 June 2016                   300,000
Total                                                                            134,974,395

23 July 2011

19 July 2011

MHM EXPLORATION PROGRESS REPORT

MHM EXPLORATION PROGRESS REPORT

ASX Release – 19 July 2011

• First stage drilling program at Cape Sorell High Purity Silica Project successfully completed,
sampling and assaying ongoing
• Highly encouraging drilling program completed at Hill 99 copper-lead-zinc prospect


HIGH PURITY SILICA DRILLING UPDATE


MHM Metals Limited (ASX:MHM) first phase diamond drilling at the Cape Sorell High Purity Silica Project has been completed. A total of six short holes intersected white quartzite over a thickness of approximately 12m based on visual appearance. The silica rich quartzite dips approximately 50° west, and drilling was designed to test the true thickness of the quartzite at the North Escarpment prospect and the potential for a more extensive silica cap over mixed sediments including sandstone and siltstone. Sampling and assaying of the drill core is continuing.

DRILLING O F HILL 99 COPPER-LEAD-ZINC PROSPECT


The two-hole 369 metre diamond-drilling program at MHM’s Hill 99 copper-lead-zinc prospect has completed, with preliminary inspection and sampling of the core by Niton XFR analyser showing highly encouraging levels of mineralisation. The target was for copper mineralisation with zinc and gold credits in either a structural or VHMS setting. The results to hand are extremely positive and the core is now being prepared for assay. 


Hole H99-04 intersected strong quartz veining from 158m to 183m within highly altered intermediate and mafic volcanic rocks with disseminated chalcopyrite (copper sulphide) though parts of this section. 


Hole H99-05 intersected strongly altered mafic volcanics throughout the hole. Intense quartz-carbonate veining is present from 118m to the end of the hole at 173m. Patchy, disseminated lead and zinc sulphides are associated with some of the veins. The intensity of the alteration and veining in both drill holes indicates that strong, mineralised hydrothermal systems have been intersected and will require follow up drilling.


Detailed studies on drill core from this and previous drill holes have shown that the stratigraphy, alteration and age of the rocks at Hill 99 are comparable with mineralised horizons at the Hellier-Fosse-Roseberry group of mines further to the north.


The drilling is consistent with MHM’s strategy to continue to progress the company’s mineral projects while assessing opportunities to engage with project development partners, divest or spin-off the mineral assets of the company at a time that maximises returns to shareholders.



Daily chart as at 19/7/2011

14 July 2011

Australian and US operational update

MHM PROGRESS REPORT 


ASX Release – 14 July 2011


• Geelong salt slag recycling plant components operating to specification
• Continued contract negotiations for US salt slag supply
• Appointment of Director of Operations, North America
• Due diligence advancing on Tennessee site selection
• Engagement with Tennessee state and local government for incentives and concessions

MHM Metals Limited (ASX:MHM) is pleased to announce that all components at the Geelong salt slag recycling plant are operating to specification. This is an important milestone for the company and paves the way for the global expansion of the business.


MHM will commence processing Alcoa’s 160,000 tonne salt slag landfill as soon as the backlog of current  stockpiles is reduced. This is in addition to the ongoing throughput of salt slag, non-salt slag and aluminium  dross from Alcoa and Sims Metal Management.


In the United States MHM continues to make progress in salt slag supply discussions with Smelter Service  Corporation, Alcoa and others. The company hopes to provide further update on this in the near future.  MHM Metals Corporation, the company’s US operating subsidiary, has appointed a Director of Operations, North America.  Mr John Pugh, formerly Vice President of Business Development and Vice President of Operations for  Smelter Service Corporation, has been appointed to the role. Mr Pugh is widely regarded as one of the leading operations executives in the US aluminium industry and will be a great asset for MHM.  Smelter Service Corporation and MHM agreed that Mr Pugh’s appointment to MHM is in the best interests of the ongoing cooperation between the companies.  Mr Pugh holds a degree in business management and has 31 years management experience in the metals industries.  This includes five years with a manganese alloy foundry and 26 years in secondary aluminium recycling, including 21 years with Smelter Service Corporation.  Mr Pugh’s appointment commenced on 1 July.


MHM continues to progress due diligence for Tennessee site selection, with a number of sites under assessment and negotiation.  The company is also positively engaged with the Tennessee state and local governments regarding concessions and incentives, and hopes to provide a further updates in the near future


Link

13 July 2011

MHMO Conversion

82,000 options has been converted into fully paid ordinary shares at $0.20 each





Daily chart as at 13/7/2011


Share price $1.135 as at 13th July 2011 
M/C $116.04m
MHM                                                                         102,234,410
MHMO expiry 31 August 2012                                  25,538,760
Unlisted Options $0.20 expiry 31 August 2012            2,131,225
                          $0.20 expiry 28 November 2013      1,100,000
                          $0.20 expiry 14 December 2013       1,000,000
                          $0.25 expiry 9 October 2014              370,000
                          $0.28 expiry 30 November 2014       1,900,000
                          $0.28 expiry 4 January 2015                100,000
                          $0.85 expiry 6 October 2015               300,000
                          $1.80 expiry 20 June 2016                   300,000
Total                                                                            134,974,395

12 July 2011

MHMO Conversion

250,000 options has been converted into fully paid ordinary shares at $0.20 each





Daily chart as at 12/7/2011


Share price $1.115 as at 12th July 2011 
M/C $113.90m
MHM                                                                         102,152,410
MHMO expiry 31 August 2012                                  25,620,760
Unlisted Options $0.20 expiry 31 August 2012            2,131,225
                          $0.20 expiry 28 November 2013      1,100,000
                          $0.20 expiry 14 December 2013       1,000,000
                          $0.25 expiry 9 October 2014              370,000
                          $0.28 expiry 30 November 2014       1,900,000
                          $0.28 expiry 4 January 2015                100,000
                          $0.85 expiry 6 October 2015               300,000
                          $1.80 expiry 20 June 2016                   300,000
Total                                                                            134,974,395