23 February 2012

MHM Company Update


MHM UPDATE

ASX Release – 23 February 2012

• 24-hour  processing  underway at Australian  salt cake recycling 
operations
• Current daily plant throughput processing all new material received, in 
addition to 35-40 bags per day of partly processed stockpiled salt cake 
• Daily throughput to increase as new staff gain additional experience
• Potential Alcoa shutdown of Point Henry Smelter would have no impact 
on MHM’s operations
• First AL80 export shipment of 500 tonnes scheduled for 5 March 2012
• Acquisition of  115-acre site for construction of first US salt cake and 
black dross recycling facility
• US plant design and layout complete, preliminary engineering and 
permitting underway
• Timeframes and capital cost of first US facility to be confirmed with US 
engineering consultants
• Preliminary site works commenced
• Additional US supply contract negotiations ongoing and positive
• Project finance favouring non-dilutionary mechanisms. New York 
roadshow commencing 28 February to increase investor awareness and 
on-market support 

AUSTRALIAN ALUMINIUM OPERATIONS UPDATE


Twenty-four hour processing is underway at  the  Geelong salt  cake recycling 
facility.  Current plant throughput is processing all salt cake being  received,  in 
addition to 35-40 bags per day of partly-processed stockpiled salt cake.  Each 
bag of stockpiled material weighs approximately 1.5 tonnes, and the 10,000 
tonne stockpile is expected to take about 3 months to process.  Current daily 
plant throughput is expected to increase as new employees continue to gain 
experience.    Updates of processing rates will be provided by the company.  


When reprocessing the stockpile of partly-processed salt cake is completed, Alreco (MHM’s subsidiary) will 
commence processing Alcoa’s 160,000 tonne salt cake landfill. When landfill processing commences Alreco’s 
earnings are expected to increase in line with the forecast EBITDA of $8 million per annum. 


The potential shut down of Alcoa’s Point Henry Smelter would have no impact on MHM.  All of Alcoa’s 
Australian salt cake is produced at the Yennora Rolling Mill in New South Wales.


Impex has advised that customs paperwork relating to export of AL80, Alreco’s aluminium oxide product, has 
been finalised and that the first shipment of 500 tonnes will depart the Geelong facility on 5 March 2012. The 
initial 500 tonne shipment was the initial volume agreed for shipment by customs, and this will ramp up to 
ensure that all Australian AL80 is exported.  


The completion of customs paperwork is a major achievement for MHM as considerable effort was devoted to 
achieve this goal. The delays were a bureaucratic matter and unrelated to the desire of the end user to 
purchase the product.  While Impex has exclusivity for AL80 only within Australia, it has expressed interest in 
also purchasing all AL80 produced in the US.  MHM has received expressions of interest from other 
companies about purchasing all US-produced AL80.



US ALUMINIUM OPERATIONS UPDATE


US subsidiary MHM Metals Corporation has acquired a 115-acre landholding in Russellville, Kentucky. The 
$838,000 purchase price was funded from existing cash reserves. The site contains existing buildings that 
will decrease the time and expense of plant construction and the site is zoned correctly for its purpose. 
Plant layout and design for the Russellville facility has now been completed and management is working with 
engineering consultants to confirm capital cost and timeframe for completion.  The existing buildings are 
ideally suited for the processing plant, and there is much enthusiasm  in  the  management  team  for  the 
property.  Environmental permitting applications are being prepared and preliminary civil site works, 
renovations of the office facilities and preparation for expedited construction of the rail spur are underway. 
MHM has a conservative preliminary budget estimate of US$25 million for construction of its 250,000 tonne 
per annum plant, though it is expected that the existing site infrastructure and availability of second-hand 
processing equipment could reduce this figure below US$20 million. Targeted earnings for this first US 
facility for salt cake and black dross processing, and aluminium oxide sales and ancillary activities is US$25 
million per annum when operating at full capacity. MHM expects the plant will operate at full capacity of 
250,000 tonnes per annum within 12 months of commissioning. 


MHM continues to negotiate additional supply contracts, and progress is positive.  Management also 
continues to assess the viability of landfilled/stockpiled salt cake for recycling.  The company is examining
opportunities to acquire large volumes of aluminium oxide to produce AL80 for export and additional 
revenue generation.


Consideration of project-financing options is underway and will be finalised when the plant capital cost and 
drawdown schedule are confirmed. Management is confident that a number of options will be available.  As 
always, management is keen to minimise any shareholder dilution to maximise Earnings Per Share and share 
price. 


A New York investor roadshow will commence on 28 February 2012 to inform and engage new investors with 
the MHM story and continue to support the share price.  A number of broking houses are expressing interest 
in publishing research on MHM, which should also benefit the company.


SILICA DIVISION UPDATE


MHM has engaged a corporate adviser to assist with the potential spin-off of the company’s silica division 
and continues to make progress. Another priority is to secure offtake contracts for lump silica and silica flour 
to help underwrite the development of a Tasmanian silicon smelter.   


Considerable effort has also been devoted to securing additional high purity silica reserves to help fast-track 
project development, offtake negotiations and lower production costs.


No comments:

Post a Comment